Assessment Year | 2022 |
---|---|
Principal Product | Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
40,000
ft2
|
Annual Production | 500,000
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $106,664 | 1,464,480 |
kWh
|
$0.073 |
Electricity Demand | $13,208 | 2,220 |
kW-mo/yr
|
$5.95 |
Electricity Fees | $7,750 | - |
|
- |
Natural Gas | $206,577 | 32,061 |
MMBtu
|
$6.44 |
TOTAL YEARLY COSTS | $334,200 | |||
RECOMMENDED SAVINGS* | $5,947 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,947 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $643 | - | - | - |
$643
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $954 | $2,680 |
$954
13,097
kWh
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,686 | $122 |
$1,516
20,817
kWh
|
$170
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,664 | $2,080 |
$2,396
32,895
kWh
|
$268
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $5,947 | $4,882 |
$4,866
66,809
kWh
|
$438
-
kW-mo/yr
|
$643
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,947 | $4,882 |
$4,866
66,809
kWh
|
$438
-
kW-mo/yr
|
$643
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs