ITAC Assessment: UD0983
ITAC logo
ITAC Assessment: UD0983
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product beer
NAICS 312120: Breweries
SIC 2082: Malt Beverages
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 24,000
ft2
Annual Production 40,000
bbl
Production Hrs. Annual 3,120
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $99,404 1,097,880
kWh
Natural Gas $33,080 5,027
MMBtu
Waste Disposal Costs
Water Usage $21,107 7,473
Tgal
Water Disposal $47,289 7,473
Tgal
TOTAL YEARLY COSTS $200,880
RECOMMENDED SAVINGS* $23,646 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,289

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4239: Eliminate or reduce compressed air usage $390 $50 $390
4,216
kWh
-
02 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $13,719 $2,500 $13,719
148,200
kWh
-
03 2.2625: Chill water to the highest temperature possible $1,019 $4,500 $427
4,615
kWh
$592
-
MMBtu
04 2.2414: Use waste heat from hot flue gases to preheat $4,393 $6,000 - $4,393
-
MMBtu
05 2.1233: Analyze flue gas for proper air/fuel ratio $2,115 - - $2,115
-
MMBtu
06 2.2211: Use optimum temperature $836 - - $836
-
MMBtu
07 2.2136: Install / repair insulation on steam lines $819 $1,100 - $819
-
MMBtu
08 2.2211: Use optimum temperature $355 - - $355
-
MMBtu
TOTAL RECOMMENDED $23,646 $14,150 $14,536
157,031
kWh
$9,110
-
MMBtu
TOTAL IMPLEMENTED $3,289 $1,100 - $3,289
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs