ITAC Assessment: UW0025
ITAC logo
ITAC Assessment: UW0025
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Fiberglass Showers and Tubs
NAICS 327110: Pottery, Ceramics, and Plumbing Fixture Manufacturing
SIC 3261: Vitreous China Plumbing Fixtures and China and Earthenware Fittings and Bathroom Accessories
Sales Range $50
M
to 100
M
# of Employees 152
Plant Area 176,000
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 3,000
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $325,375 4,042,864
kWh
Natural Gas $401,079 40,238
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $85,047 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,186

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.2443: Re-use or recycle hot or cold process exhaust air $52,500 $78,750 - - $52,500
-
MMBtu
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $16,361 $17,335 $11,161
186,025
kWh
- - $5,200
03 2.2211: Use optimum temperature $13,200 $19,800 - - $13,200
-
MMBtu
-
04 2.4151: Develop a repair/replace policy $2,986 $6,091 $1,199
19,985
kWh
$1,787
-
kW-mo/yr
- -
TOTAL RECOMMENDED $85,047 $121,976 $12,360
206,010
kWh
$1,787
-
kW-mo/yr
$65,700
-
MMBtu
$5,200
TOTAL IMPLEMENTED $16,186 $25,891 $1,199
19,985
kWh
$1,787
-
kW-mo/yr
$13,200
-
MMBtu
-