Assessment Year | 2009 |
---|---|
Principal Product | Aerospace Composites |
NAICS | 336411: Aircraft Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
140,000
ft2
|
Annual Production | 13,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,950 | 1,875,030 |
kWh
|
$0.038 |
Electricity Demand | $44,447 | 13,268 |
kW-mo/yr
|
$3.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,767 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,565 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,517 | $48,000 |
$8,646
183,575
kWh
|
$1,262
-
kW-mo/yr
|
$1,609 | - | - | |
02 | 2.3137: Use power during off-peak periods | $4,202 | $400 |
$(-9,702.0)
-
kWh
|
$13,904
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,586 | - |
$2,857
79,365
kWh
|
$509
-
kW-mo/yr
|
- | - | $(-780.0) | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $889 | - |
$754
20,947
kWh
|
$135
-
kW-mo/yr
|
- | - | - | |
05 | 3.4151: Minimize water usage | $3,573 | - | - | - | - |
$3,573
-
Tgal
|
- | |
TOTAL RECOMMENDED | $22,767 | $48,400 |
$2,555
283,887
kWh
|
$15,810
-
kW-mo/yr
|
$1,609 |
$3,573
-
Tgal
|
$(-780.0) | ||
TOTAL IMPLEMENTED | $18,565 | $48,000 |
$12,257
283,887
kWh
|
$1,906
-
kW-mo/yr
|
$1,609 |
$3,573
-
Tgal
|
$(-780.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs