ITAC Assessment: NC0653
ITAC logo
ITAC Assessment: NC0653
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Valve actuators
NAICS 333995: Fluid Power Cylinder and Actuator Manufacturing
SIC 3593: Fluid Power Cylinders and Actuators
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 325,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,000,948 18,079,901
kWh
Electricity Demand $406,211 33,577
kW-mo/yr
Electricity Fees $(-149,634.0) -
Natural Gas $236,799 44,817
MMBtu
Waste Disposal Costs
Water Usage $10,000 1,000
Tgal
TOTAL YEARLY COSTS $1,504,324
RECOMMENDED SAVINGS* $424,726 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Ancillary Material Cost Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $19,814 $4,460 $19,345
349,437
kWh
- $469
-
MMBtu
- -
02 2.4237: Substitute compressed air cooling with water or air cooling $22,483 $4,000 - - $22,483
-
MMBtu
- -
03 2.7232: Replace existing hvac unit with high efficiency model $382,429 $2,300,000 $116,938
2,112,328
kWh
$55,491
-
kW-mo/yr
- $(-40,000.0)
-
Tgal
$250,000
TOTAL RECOMMENDED $424,726 $2,308,460 $136,283
2,461,765
kWh
$55,491
-
kW-mo/yr
$22,952
-
MMBtu
$(-40,000.0)
-
Tgal
$250,000
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs