ITAC Assessment: UW0013
ITAC logo
ITAC Assessment: UW0013
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Candy and Confectionary
NAICS 311352: Confectionery Manufacturing from Purchased Chocolate
SIC 2064: Candy and Other Confectionery Products
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 9,212
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Hawaii

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $10,891 127,666
kWh
Electricity Demand $3,351 1,168
kW-mo/yr
Electricity Fees $8,807 -
LPG $12,756 450
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,518 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $544

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.7262: Separate controls of air handlers from ac/ heating systems $3,676 $593 - - $3,676
-
MMBtu
02 4.611: Begin a practice of predictive / preventative maintenance $2,365 $130 $2,365
13,140
kWh
- -
03 2.4321: Upgrade obsolete equipment $1,913 $6,000 $147
817
kWh
- $1,766
-
MMBtu
04 2.9113: Use solar heat for heat $1,498 $4,250 - - $1,498
-
MMBtu
05 2.4231: Reduce the pressure of compressed air to the minimum required $544 - $463
2,576
kWh
$81
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $522 $1,787 $417
2,370
kWh
$105
-
kW-mo/yr
-
TOTAL RECOMMENDED $10,518 $12,760 $3,392
18,903
kWh
$186
-
kW-mo/yr
$6,940
-
MMBtu
TOTAL IMPLEMENTED $544 - $463
2,576
kWh
$81
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs