| Assessment Year | 2007 |
|---|---|
| Principal Product | Custom Cardboard Boxes |
| NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $50 M to 100M |
| # of Employees | 230 |
| Plant Area |
475,000
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 8,112
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $396,662 | 4,965,000 |
kWh
|
$0.080 |
| Natural Gas | $84,516 | 7,846 |
MMBtu
|
$10.77 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $56,524 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,106 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6242: Minimize operation of equipment maintained in standby condition | $29,806 | $4,759 |
$29,806
485,949
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,096 | $1,900 |
$7,166
133,140
kWh
|
$930
-
kW-mo/yr
|
- | |
| 03 | 2.6121: Reduce hot water temperature to the minimum required | $6,191 | $10,550 |
$5,166
19,049
kWh
|
$1,025
-
kW-mo/yr
|
- | |
| 04 | 2.3212: Optimize plant power factor | $3,834 | $12,330 | - | - | $3,834 | |
| 05 | 2.4133: Use most efficient type of electric motors | $2,403 | $4,470 |
$2,089
34,052
kWh
|
$314
-
kW-mo/yr
|
- | |
| 06 | 2.7135: Install occupancy sensors | $2,289 | $3,340 |
$2,017
32,811
kWh
|
$272
-
kW-mo/yr
|
- | |
| 07 | 2.9112: Use solar heat to heat water | $1,600 | $4,450 |
$1,523
24,836
kWh
|
$77
-
kW-mo/yr
|
- | |
| 08 | 2.4151: Develop a repair/replace policy | $1,318 | $597 |
$1,168
19,050
kWh
|
$150
-
kW-mo/yr
|
- | |
| 09 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $987 | $1,725 |
$888
14,472
kWh
|
$99
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $56,524 | $44,121 |
$49,823
763,359
kWh
|
$2,867
-
kW-mo/yr
|
$3,834 | ||
| TOTAL IMPLEMENTED | $14,106 | $10,307 |
$12,440
219,053
kWh
|
$1,666
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs