Assessment Year | 1999 |
---|---|
Principal Product | Injection Molded Plastics |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 140 |
Plant Area |
40,000
ft2
|
Annual Production | 2,200,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $105,648 | 1,818,288 |
kWh
|
$0.058 |
Electricity Demand | $42,392 | 4,712 |
kW-mo/yr
|
$9.00 |
Electricity Fees | $13,924 | - |
|
- |
Natural Gas | $14,883 | 2,521 |
MMBtu
|
$5.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,385 | $2,237 |
$1,083
16,999
kWh
|
$302
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7496: Install partitions to reduce size of conditioned space | $4,659 | $5,000 | - | - |
$4,659
-
MMBtu
|
- | - | - | |
03 | 4.611: Begin a practice of predictive / preventative maintenance | $2,000 | $500 | - | - | - | - | - | $2,000 | |
04 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,170 | $1,000 | - | - | - | - | - | $1,170 | |
05 | 4.611: Begin a practice of predictive / preventative maintenance | $3,000 | $300 | - | - | - | - | - | $3,000 | |
06 | 4.424: Improve space comfort conditioning | $2,340 | $5,000 | - | - | - | - | - | $2,340 | |
07 | 3.7131: Use a rag recycle service | $336 | $200 | - | - | - | - | $336 | - | |
08 | 3.4151: Minimize water usage | $300 | $250 | - | - | - |
$300
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $15,190 | $14,487 |
$1,083
16,999
kWh
|
$302
-
kW-mo/yr
|
$4,659
-
MMBtu
|
$300
-
Tgal
|
$336 | $8,510 | ||
TOTAL IMPLEMENTED | $5,000 | $800 | - | - | - | - | - | $5,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs