| Assessment Year | 2026 |
|---|---|
| Principal Product | Pullups |
| NAICS | 322291: Sanitary Paper Product Manufacturing |
| SIC | 2676: Sanitary Paper Products |
| Sales Range | greater than $500 M |
| # of Employees | 100 |
| Plant Area |
1,300,000
ft2
|
| Annual Production | 20,000,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $775,663 | 23,665,920 |
kWh
|
$0.033 | |
| Electricity Demand | $664,471 | 41,844 |
kW-mo/yr
|
$15.88 | |
| Electricity Fees | $479,162 | - |
|
- | |
| Natural Gas | $168,468 | 24,145 |
MMBtu
|
$6.98 | |
| Waste Disposal Costs | |||||
| Water Usage | $45,081 | 14,714 |
Tgal
|
$3.06 | |
| TOTAL YEARLY COSTS | $2,132,845 | ||||
| RECOMMENDED SAVINGS* | $238,847 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2623: Minimize condenser cooling water temperature | $8,440 | $18,000 |
$8,440
257,342
kWh
|
- | - | - | - | |
| 02 | 2.3113: Make ice during off peak hours for cooling | $56,998 | $810,000 | - | $56,998 | - | - | - | |
| 03 | 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation | $64,472 | $177,600 |
$3,397
103,584
kWh
|
- |
$61,075
-
MMBtu
|
- | - | |
| 04 | 3.4151: Minimize water usage | $56,001 | $110,000 | - | - | - |
$329
-
Tgal
|
$55,672 | |
| 05 | 2.7135: Install occupancy sensors | $6,228 | $12,600 |
$6,228
185,523
kWh
|
- | - | - | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $46,708 | $314,394 |
$46,708
1,424,040
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $238,847 | $1,442,594 |
$64,773
1,970,489
kWh
|
$56,998 |
$61,075
-
MMBtu
|
$329
-
Tgal
|
$55,672 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs