| Assessment Year | 2026 |
|---|---|
| Principal Product | Health & wellness product |
| NAICS | 493110: General Warehousing and Storage |
| SIC | 4225: General Warehousing and Storage |
| Sales Range | $100 M to 500M |
| # of Employees | 160 |
| Plant Area |
327,000
ft2
|
| Annual Production | 60,000,000
units
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $68,915 | 1,884,300 |
kWh
|
$0.037 | |
| Electricity Demand | $92,792 | 5,579 |
kW-mo/yr
|
$16.63 | |
| Electricity Fees | $76,790 | - |
|
- | |
| Natural Gas | $155,619 | 22,486 |
MMBtu
|
$6.92 | |
| Waste Disposal Costs | |||||
| Solid Waste (non-haz) | $214,500 | 163,800 |
lb
|
$1.31 | |
| TOTAL YEARLY COSTS | $608,616 | ||||
| RECOMMENDED SAVINGS* | $144,760 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7264: Interlock heating and air conditioning systems to prevent simultaneous operation | $103,610 | $100,000 | - | - | - |
$103,610
-
MMBtu
|
- | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,000 | $9,600 | - |
$5,000
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.3141: Use battery storage for demand control | $9,420 | $20,000 | - | - | $9,420 | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $880 | $740 |
$880
24,120
kWh
|
- | - | - | - | - | |
| 05 | 3.1162: Use less wasteful packaging | $14,630 | $44,660 | - | - | - | - |
$14,200
-
lb
|
$430 | |
| 06 | 2.7261: Install timers and/or thermostats | $1,290 | $1,800 | - | - | - |
$1,290
-
MMBtu
|
- | - | |
| 07 | 2.7221: Lower temperature during the winter season and vice-versa | $8,450 | $11,400 | - | - | - |
$8,450
-
MMBtu
|
- | - | |
| 08 | 2.7221: Lower temperature during the winter season and vice-versa | $510 | $1,610 |
$245
6,540
kWh
|
- | - |
$265
-
MMBtu
|
- | - | |
| 09 | 4.821: Pay bills on time to avoid late fees | $970 | $1,000 | - | - | $970 | - | - | - | |
| TOTAL RECOMMENDED | $144,760 | $190,810 |
$1,125
30,660
kWh
|
$5,000
-
kW-mo/yr
|
$10,390 |
$113,615
-
MMBtu
|
$14,200
-
lb
|
$430 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs