Assessment Year | 1989 |
---|---|
Principal Product | PRINTED PLASTIC FILM |
NAICS |
n/a
|
SIC | 2673: Plastics, Foil, and Coated Paper Bags |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
n/a
|
Annual Production | 4,400,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $107,743 | 1,800,997 |
kWh
|
$0.060 |
Natural Gas | $35,555 | 6,368 |
MMBtu
|
$5.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,619 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,506 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,492 | $832 |
$3,492
58,324
kWh
|
- | |
02 | 2.2428: Use flue gases in radiant heater for space heating, ovens, etc | $4,130 | $15,000 |
$(-630.0)
(-10,551)
kWh
|
$4,760
-
MMBtu
|
|
03 | 2.4133: Use most efficient type of electric motors | $388 | $379 |
$388
6,448
kWh
|
- | |
04 | 2.7226: Use computer programs to optimize hvac performance | $393 | $500 |
$393
16,706
kWh
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $551 | - |
$551
9,379
kWh
|
- | |
06 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $590 | $580 |
$590
9,672
kWh
|
- | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $910 | - |
$910
15,240
kWh
|
- | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $165 | $125 |
$165
2,638
kWh
|
- | |
TOTAL RECOMMENDED | $10,619 | $17,416 |
$5,859
107,856
kWh
|
$4,760
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,506 | $1,336 |
$5,506
92,029
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs