Assessment Year | 2025 |
---|---|
Principal Product | Ready-Mix Concrete |
NAICS | 327320: Ready-Mix Concrete Manufacturing |
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $50 M to 100M |
# of Employees | 87 |
Plant Area |
19,796
ft2
|
Annual Production | 330,000
ton
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Wyoming |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,485 | 711,480 |
kWh
|
$0.039 |
Electricity Demand | $25,833 | 3,458 |
kW-mo/yr
|
$7.47 |
Electricity Fees | $1,633 | - |
|
- |
Natural Gas | $149,839 | 12,383 |
MMBtu
|
$12.10 |
Other Energy | $734,219 | 27,265 |
MMBtu
|
$26.93 |
TOTAL YEARLY COSTS | $939,009 | |||
RECOMMENDED SAVINGS* | $208,034 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8226: Increase efficiency of trucks | $126,055 | $584,355 | - | - |
$126,055
-
MMBtu
|
- | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $59,940 | $100,340 | - | - |
$11,310
-
MMBtu
|
$48,630 | |
03 | 2.1321: Replace fossil fuel equipment with electrical equipment | $18,569 | $141,050 |
$(-43,971.0)
(-1,138,250)
kWh
|
$(-42,070.0)
-
kW-mo/yr
|
$104,610
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,270 | $1,800 |
$1,270
32,550
kWh
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,200 | $15,740 |
$1,877
48,590
kWh
|
$323
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $208,034 | $843,285 |
$(-40,824.0)
(-1,057,110)
kWh
|
$(-41,746.6)
-
kW-mo/yr
|
$241,975
-
MMBtu
|
$48,630 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs