Assessment Year | 2025 |
---|---|
Principal Product | Steel Investment Casts |
NAICS | 331512: Steel Investment Foundries |
SIC | 3324: Steel Investment Foundries |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
18,900
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 4,192
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $180,205 | 1,659,780 |
kWh
|
$0.11 |
Electricity Fees | $54,647 | - |
|
- |
Natural Gas | $122,739 | 13,528 |
MMBtu
|
$9.07 |
TOTAL YEARLY COSTS | $357,591 | |||
RECOMMENDED SAVINGS* | $74,190 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8124: Hire energy manager | $11,100 | $4,800 |
$18,100
166,000
kWh
|
- |
$12,200
-
MMBtu
|
$(-19,200.0) | - | |
02 | 2.8113: Purchase gas directly from a contract gas supplier | $21,900 | $12,000 | - | - | - | - | $21,900 | |
03 | 2.8114: Change rate schedules or other changes in utility service | $12,800 | $9,600 | - | $12,800 | - | - | - | |
04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $7,300 | $2,900 |
$7,300
67,000
kWh
|
- | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $790 | $5,550 |
$790
7,200
kWh
|
- | - | - | - | |
06 | 2.2442: Preheat combustion air with waste heat | $3,270 | $22,800 | - | - |
$3,270
-
MMBtu
|
- | - | |
07 | 2.6218: Turn off equipment when not in use | $9,350 | $3,000 | - | - |
$9,350
-
MMBtu
|
- | - | |
08 | 2.2511: Insulate bare equipment | $3,030 | $15,460 | - | - |
$3,030
-
MMBtu
|
- | - | |
09 | 2.7229: Air condition only space necessary | $1,130 | $2,230 |
$1,130
10,400
kWh
|
- | - | - | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,520 | $9,240 |
$3,520
32,300
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $74,190 | $87,580 |
$30,840
282,900
kWh
|
$12,800 |
$27,850
-
MMBtu
|
$(-19,200.0) | $21,900 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs