Assessment Year | 2024 |
---|---|
Principal Product | Agricultural Trailers |
NAICS | 336212: Truck Trailer Manufacturing |
SIC | 3715: Truck Trailers |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
35,147
ft2
|
Annual Production | 278
units
|
Production Hrs. Annual | 2,739
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $10,822 | 234,126 |
kWh
|
$0.046 |
Electricity Demand | $5,404 | 1,081 |
kW-mo/yr
|
$5.00 |
Electricity Fees | $40 | - |
|
- |
Natural Gas | $10,054 | 1,292 |
MMBtu
|
$7.78 |
LPG | $7,426 | 114 |
MMBtu
|
$64.91 |
Fuel Oil #2 | $16,025 | 433 |
MMBtu
|
$37.02 |
Fuel Oil #4 | $55,580 | 2,387 |
MMBtu
|
$23.28 |
TOTAL YEARLY COSTS | $105,351 | |||
RECOMMENDED SAVINGS* | $45,850 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #4 Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $980 | $2,600 |
$836
17,940
kWh
|
$144
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,740 | $1,270 |
$1,715
37,080
kWh
|
$25
-
kW-mo/yr
|
- | - | - | - | |
03 | 3.1194: Use automatic flow control | $820 | $4,250 |
$694
15,090
kWh
|
$126
-
kW-mo/yr
|
- | - | - | - | |
04 | 4.111: Add equipment/ operators to reduce production bottleneck | $33,420 | $319,250 |
$(-620.0)
(-13,440)
kWh
|
- |
$2,480
-
MMBtu
|
$26,870
-
MMBtu
|
$4,690 | - | |
05 | 2.1321: Replace fossil fuel equipment with electrical equipment | $6,380 | $133,800 |
$(-1,050.0)
(-22,770)
kWh
|
- |
$7,430
-
MMBtu
|
- | - | - | |
06 | 2.4322: Use or replace with energy efficient substitutes | $940 | $3,000 | - | - | - | - | - | $940 | |
07 | 2.4322: Use or replace with energy efficient substitutes | $1,570 | $9,360 |
$1,570
34,320
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $45,850 | $473,530 |
$3,145
68,220
kWh
|
$295
-
kW-mo/yr
|
$9,910
-
MMBtu
|
$26,870
-
MMBtu
|
$4,690 | $940 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #4 Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs