Assessment Year | 2023 |
---|---|
Principal Product | Candy |
NAICS | 311340: Nonchocolate Confectionery Manufacturing |
SIC | 2064: Candy and Other Confectionery Products |
Sales Range | $100 M to 500M |
# of Employees | 215 |
Plant Area |
220,000
ft2
|
Annual Production | 36,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $413,196 | 12,064,141 |
kWh
|
$0.034 | |
Electricity Demand | $459,780 | 48,808 |
kW-mo/yr
|
$9.42 | |
Electricity Fees | $106,866 | - |
|
- | |
Natural Gas | $559,770 | 68,160 |
MMBtu
|
$8.21 | |
Waste Disposal Costs | |||||
Water Usage | $66,680 | 35,240 |
Tgal
|
$1.89 | |
Water Disposal | $868,830 | 35,240 |
Tgal
|
$24.65 | |
TOTAL YEARLY COSTS | $2,475,122 | ||||
RECOMMENDED SAVINGS* | $666,144 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $664,350 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9141: Install anaerobic digester | $648,030 | $7,400,000 | - | - |
$430
-
MMBtu
|
$647,600
-
Tgal
|
|
02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $9,500 | $51,330 |
$8,596
252,812
kWh
|
$904
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $4,807 | $8,910 |
$3,484
102,485
kWh
|
$1,323
-
kW-mo/yr
|
- | - | |
04 | 2.4224: Upgrade controls on compressors | $2,013 | $1,020 |
$1,606
47,229
kWh
|
$407
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,794 | $5,550 |
$1,302
38,298
kWh
|
$492
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $666,144 | $7,466,810 |
$14,988
440,824
kWh
|
$3,125
-
kW-mo/yr
|
$430
-
MMBtu
|
$647,600
-
Tgal
|
||
TOTAL IMPLEMENTED | $664,350 | $7,461,260 |
$13,686
402,526
kWh
|
$2,634
-
kW-mo/yr
|
$430
-
MMBtu
|
$647,600
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs