ITAC Assessment: AM0827
ITAC logo
ITAC Assessment: AM0827
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product gaskets, bolts and hose assemblies
NAICS 339991: Gasket, Packing, and Sealing Device Manufacturing
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $100
M
to 500
M
# of Employees 250
Plant Area 130,000
ft2
Annual Production 4,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $262,866 5,086,728
kWh
Electricity Demand $109,836 11,559
kW-mo/yr
Electricity Fees $11,460 -
Natural Gas $18,258 2,280
MMBtu
TOTAL YEARLY COSTS $402,420
RECOMMENDED SAVINGS* $26,546 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,546

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.3212: Optimize plant power factor $13,390 $30,920 - $13,390
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,760 $1,300 $6,060
131,700
kWh
$1,700
-
kW-mo/yr
-
03 2.7124: Make a practice of turning off lights when not needed $3,630 - $3,630
78,860
kWh
- -
04 2.8123: Pay utility bills on time $1,766 - - - $1,766
TOTAL RECOMMENDED $26,546 $32,220 $9,690
210,560
kWh
$15,090
-
kW-mo/yr
$1,766
TOTAL IMPLEMENTED $26,546 $32,220 $9,690
210,560
kWh
$15,090
-
kW-mo/yr
$1,766
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs