Assessment Year | 2021 |
---|---|
Principal Product | Canned Goods |
NAICS | 311422: Specialty Canning |
SIC | 2032: Canned Specialties |
Sales Range | $500 k to 1M |
# of Employees | 8 |
Plant Area |
26,900
ft2
|
Annual Production | 4,824,000
units
|
Production Hrs. Annual | 2,400
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $24,466 | 661,160 |
kWh
|
$0.037 | |
Electricity Demand | $43,338 | 2,581 |
kW-mo/yr
|
$16.79 | |
Electricity Fees | $8,556 | - |
|
- | |
Natural Gas | $15,198 | 5,141 |
MMBtu
|
$2.96 | |
Waste Disposal Costs | |||||
Water Usage | $14,707 | 4,348 |
Tgal
|
$3.38 | |
TOTAL YEARLY COSTS | $106,265 | ||||
RECOMMENDED SAVINGS* | $108,004 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $30,079 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $72,600 | $4,000 | - | - | - | $72,600 | - | |
02 | 3.6192: Use a less expensive method of waste removal | $27,935 | $2,000 | - | - | - | - | $27,935 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,891 | $1,233 |
$1,783
48,180
kWh
|
$1,108
-
kW-mo/yr
|
- | - | - | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,472 | $8,300 |
$(-47.4)
(-1,280)
kWh
|
- |
$1,519
-
MMBtu
|
- | - | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $1,131 | $100 |
$215
5,801
kWh
|
- |
$916
-
MMBtu
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,013 | $6,614 |
$348
9,406
kWh
|
$665
-
kW-mo/yr
|
- | - | - | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $617 | $50 |
$617
16,663
kWh
|
- | - | - | - | |
08 | 2.2511: Insulate bare equipment | $345 | $747 | - | - |
$345
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $108,004 | $23,044 |
$2,915
78,770
kWh
|
$1,773
-
kW-mo/yr
|
$2,781
-
MMBtu
|
$72,600 | $27,935 | ||
TOTAL IMPLEMENTED | $30,079 | $8,714 |
$563
15,207
kWh
|
$665
-
kW-mo/yr
|
$916
-
MMBtu
|
- | $27,935 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs