ITAC Assessment: BS0018
ITAC logo
ITAC Assessment: BS0018
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Drilling Equipment
NAICS 333517: Machine Tool Manufacturing
SIC 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds
Sales Range $10
M
to 50
M
# of Employees 68
Plant Area 24,200
ft2
Annual Production 52
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $28,594 458,760
kWh
Electricity Demand $8,814 1,553
kW-mo/yr
Natural Gas $14,452 2,087
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,410 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,826

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7492: Use proper thickness of insulation on building envelope $552 $934 - - $552
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,122 $7,317 $970
15,575
kWh
$151
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $152 $600 $152
2,540
kWh
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,152 $3,300 $1,152
18,484
kWh
- -
05 2.6218: Turn off equipment when not in use $432 $718 $432
6,935
kWh
- -
TOTAL RECOMMENDED $3,410 $12,869 $2,706
43,534
kWh
$151
-
kW-mo/yr
$552
-
MMBtu
TOTAL IMPLEMENTED $1,826 $8,851 $1,122
18,115
kWh
$151
-
kW-mo/yr
$552
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs