Assessment Year | 2023 |
---|---|
Principal Product | Active Pharmaceutical Ingredients |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 110 |
Plant Area |
56,800
ft2
|
Annual Production | 30,000
lb
|
Production Hrs. Annual | 8,520
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $308,821 | 6,047,392 |
kWh
|
$0.051 |
Electricity Demand | $135,920 | 12,243 |
kW-mo/yr
|
$11.10 |
Electricity Fees | $1,241 | - |
|
- |
Natural Gas | $102,772 | 9,000 |
MMBtu
|
$11.42 |
TOTAL YEARLY COSTS | $548,754 | |||
RECOMMENDED SAVINGS* | $20,182 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $754 | - |
$581
11,397
kWh
|
$173
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,227 | $680 |
$894
17,520
kWh
|
$333
-
kW-mo/yr
|
- | |
03 | 2.6218: Turn off equipment when not in use | $5,203 | $5,000 |
$4,409
87,997
kWh
|
$794
-
kW-mo/yr
|
- | |
04 | 2.4226: Use / purchase optimum sized compressor | $2,746 | $1,700 |
$2,107
42,048
kWh
|
$639
-
kW-mo/yr
|
- | |
05 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $10,252 | $50,000 |
$2,361
46,291
kWh
|
- |
$7,891
-
MMBtu
|
|
TOTAL RECOMMENDED | $20,182 | $57,380 |
$10,352
205,253
kWh
|
$1,939
-
kW-mo/yr
|
$7,891
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs