Assessment Year | 2020 |
---|---|
Principal Product | Bottled milk, cottage cheese, orange juice |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $1 M to 5M |
# of Employees | 300 |
Plant Area |
92,350
ft2
|
Annual Production | 10,500,000
lb
|
Production Hrs. Annual | 8,720
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $520,234 | 15,818,880 |
kWh
|
$0.033 | |
Electricity Demand | $410,617 | 30,215 |
kW-mo/yr
|
$13.59 | |
Electricity Fees | $74,307 | - |
|
- | |
Natural Gas | $270,305 | 74,100 |
MMBtu
|
$3.65 | |
Waste Disposal Costs | |||||
Water Usage | $134,355 | 88,862 |
Tgal
|
$1.51 | |
Water Disposal | $354,559 | 88,862 |
Tgal
|
$3.99 | |
Other Liquid (haz) | $825,305 | 87,413,496 |
gal
|
$0.009 | |
TOTAL YEARLY COSTS | $2,589,683 | ||||
RECOMMENDED SAVINGS* | $192,760 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $111,470 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2121: Increase amount of condensate returned | $47,740 | $212,490 | - | - | $(-1,840.0) |
$28,990
-
MMBtu
|
$5,650
-
Tgal
|
$14,940
-
Tgal
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $41,050 | $179,660 |
$26,240
795,110
kWh
|
$14,810
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $30,330 | $4,800 |
$25,050
759,060
kWh
|
$5,280
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 3.4154: Eliminate leaks in water lines and valves | $14,460 | $13,100 | - | - | - | - |
$3,970
-
Tgal
|
$10,490
-
Tgal
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,220 | $23,540 |
$5,160
156,390
kWh
|
$3,060
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $960 | $1,140 |
$610
18,550
kWh
|
$350
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.8124: Hire energy manager | $50,000 | $2,700 | - | - | - | - | - | - | $50,000 | |
TOTAL RECOMMENDED | $192,760 | $437,430 |
$57,060
1,729,110
kWh
|
$23,500
-
kW-mo/yr
|
$(-1,840.0) |
$28,990
-
MMBtu
|
$9,620
-
Tgal
|
$25,430
-
Tgal
|
$50,000 | ||
TOTAL IMPLEMENTED | $111,470 | $428,790 |
$31,400
951,500
kWh
|
$17,870
-
kW-mo/yr
|
$(-1,840.0) |
$28,990
-
MMBtu
|
$9,620
-
Tgal
|
$25,430
-
Tgal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs