ITAC Assessment: GT0111
ITAC logo
ITAC Assessment: GT0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product PRINTED MATERIALS
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $5
M
to 10
M
# of Employees 150
Plant Area
n/a
Annual Production 20,000,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $132,540 3,060,961
kWh
Natural Gas $45,700 10,758
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,031 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,031

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7111: Reduce illumination to minimum necessary levels $814 - $984
22,860
kWh
$(-170.0)
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,092 $597 $3,736
86,166
kWh
$(-644.0)
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $125 $25 $125
2,931
kWh
-
TOTAL RECOMMENDED $4,031 $622 $4,845
111,957
kWh
$(-814.0)
-
MMBtu
TOTAL IMPLEMENTED $4,031 $622 $4,845
111,957
kWh
$(-814.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs