| Assessment Year | 2019 |
|---|---|
| Principal Product | Beer |
| NAICS | 312120: Breweries |
| SIC | 2082: Malt Beverages |
| Sales Range | $500 k to 1M |
| # of Employees | 17 |
| Plant Area |
37,000
ft2
|
| Annual Production | 3,000
bbl
|
| Production Hrs. Annual | 1,872
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $5,589 | 152,880 |
kWh
|
$0.037 | |
| Electricity Demand | $8,930 | 545 |
kW-mo/yr
|
$16.39 | |
| Natural Gas | $18,090 | 2,690 |
MMBtu
|
$6.73 | |
| Waste Disposal Costs | |||||
| Water Usage | $31,650 | 930 |
Tgal
|
$34.03 | |
| Gaseous Waste | $6,933 | 26,000 |
lb
|
$0.27 | |
| TOTAL YEARLY COSTS | $71,193 | ||||
| RECOMMENDED SAVINGS* | $13,412 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $2,928 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Gaseous Waste Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.1175: Use a different or recycled raw material | $6,933 | $50,000 | - | - | - |
$6,933
-
lb
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,811 | $160 | - | - |
$2,811
-
MMBtu
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,726 | $2,762 |
$743
20,072
kWh
|
$901
-
kW-mo/yr
|
- | - | $82 | |
| 04 | 2.7444: Close holes and openings in building such as broken windows | $740 | $800 | - | - |
$740
-
MMBtu
|
- | - | |
| 05 | 4.661: Level zero – install control systems for existing equipment | $451 | $1,100 |
$451
12,190
kWh
|
- | - | - | - | |
| 06 | 3.1161: Eliminate/reduce an operation | $445 | - | - | - | - |
$445
-
lb
|
- | |
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $306 | $260 |
$306
8,275
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $13,412 | $55,082 |
$1,500
40,537
kWh
|
$901
-
kW-mo/yr
|
$3,551
-
MMBtu
|
$7,378
-
lb
|
$82 | ||
| TOTAL IMPLEMENTED | $2,928 | $4,122 |
$1,500
40,537
kWh
|
$901
-
kW-mo/yr
|
- |
$445
-
lb
|
$82 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Gaseous Waste Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs