Assessment Year | 2019 |
---|---|
Principal Product | Molded Plastic Parts |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 95 |
Plant Area |
61,900
ft2
|
Annual Production | 6,100
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $139,171 | 3,812,639 |
kWh
|
$0.037 | |
Electricity Demand | $107,676 | 6,632 |
kW-mo/yr
|
$16.24 | |
Electricity Fees | $63,345 | - |
|
- | |
Natural Gas | $3,853 | 507 |
MMBtu
|
$7.60 | |
Waste Disposal Costs | |||||
Water Usage | $10,470 | 2,084 |
Tgal
|
$5.02 | |
TOTAL YEARLY COSTS | $324,515 | ||||
RECOMMENDED SAVINGS* | $73,867 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $36,471 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2612: Use cooling tower water instead of refrigeration | $33,354 | $66,174 |
$20,507
561,817
kWh
|
$12,847
-
kW-mo/yr
|
- | - | |
02 | 3.5311: Recover and reuse waste material | $12,915 | $9,000 | - | - | - | $12,915 | |
03 | 2.8121: Apply for tax-free status for energy purchases | $10,938 | $2,000 | - | - | $10,938 | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,593 | $32,661 |
$5,977
163,737
kWh
|
$3,616
-
kW-mo/yr
|
- | - | |
05 | 2.3134: Shift from daytime to nighttime operation | $2,562 | $4,000 | - |
$2,562
-
kW-mo/yr
|
- | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $1,817 | $3,415 |
$811
22,220
kWh
|
$1,005
-
kW-mo/yr
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,480 | $3,445 |
$785
21,514
kWh
|
$695
-
kW-mo/yr
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,208 | $231 |
$749
20,519
kWh
|
$459
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $73,867 | $120,926 |
$28,830
789,807
kWh
|
$21,184
-
kW-mo/yr
|
$10,938 | $12,915 | ||
TOTAL IMPLEMENTED | $36,471 | $47,307 |
$7,537
206,476
kWh
|
$5,080
-
kW-mo/yr
|
$10,938 | $12,915 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs