| Assessment Year | 2000 |
|---|---|
| Principal Product | Textiles |
| NAICS |
n/a
|
| SIC | 2299: Textile goods, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 275 |
| Plant Area |
185,000
ft2
|
| Annual Production | 4,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $415,813 | 5,752,052 |
kWh
|
$0.072 |
| Electricity Demand | $115,252 | 12,626 |
kW-mo/yr
|
$9.13 |
| Electricity Fees | $17,069 | - |
|
- |
| LPG | $108,781 | 13,694 |
MMBtu
|
$7.94 |
| Fuel Oil #6 | $144,146 | 37,868 |
MMBtu
|
$3.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $69,391 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $27,427 | $27,427 |
$11,059
152,989
kWh
|
$21,693
-
kW-mo/yr
|
$(-5,325.0)
-
MMBtu
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $12,375 | $13,500 |
$20,221
212,192
kWh
|
- |
$(-7,846.0)
-
MMBtu
|
- | - | |
| 03 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $11,743 | $35,073 | - | - |
$11,743
-
MMBtu
|
- | - | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $5,346 | $7,200 |
$5,346
55,979
kWh
|
- | - | - | - | |
| 05 | 3.5311: Recover and reuse waste material | $7,500 | $3,600 | - | - | - |
$7,500
-
lb
|
- | |
| 06 | 4.131: Modify process to reduce material use/cost | $5,000 | $15,000 | - | - | - | - | $5,000 | |
| TOTAL RECOMMENDED | $69,391 | $101,800 |
$36,626
421,160
kWh
|
$21,693
-
kW-mo/yr
|
$(-1,428.0)
-
MMBtu
|
$7,500
-
lb
|
$5,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs