ITAC Assessment: TN0360
ITAC logo
ITAC Assessment: TN0360
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product BOOTS,VULCANIZ. PRESSES
NAICS
n/a
SIC 3143: Men's Footwear, Except Athletic
Sales Range $10
M
to 50
M
# of Employees 265
Plant Area
n/a
Annual Production 592,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $175,418 3,526,964
kWh
Fuel Oil #2 $18,190 2,996
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,952 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,821

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
01 2.7123: Keep lamps and reflectors clean $10,266 $24,045 $9,906
198,124
kWh
- $360
02 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $4,620 $1,150 $4,620
92,321
kWh
- -
03 2.2511: Insulate bare equipment $4,865 $1,211 $4,865
97,304
kWh
- -
04 2.2163: Use minimum steam operating pressure $1,135 - - $1,135
-
MMBtu
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,550 $600 $2,550
50,996
kWh
- -
06 2.6212: Turn off equipment during breaks, reduce operating time $1,685 $1,700 $1,685
33,705
kWh
- -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $703 - $703
14,068
kWh
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,128 $900 $1,128
22,567
kWh
- -
TOTAL RECOMMENDED $26,952 $29,606 $25,457
509,085
kWh
$1,135
-
MMBtu
$360
TOTAL IMPLEMENTED $11,821 $4,350 $10,686
213,657
kWh
$1,135
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs