| Assessment Year | 2026 |
|---|---|
| Principal Product | Processed Steel and Aluminum |
| NAICS | 331221: Rolled Steel Shape Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 45 |
| Plant Area |
104,000
ft2
|
| Annual Production | 77,000
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $46,498 | 501,362 |
kWh
|
$0.093 | |
| Electricity Demand | $25,191 | 10,655 |
kW-mo/yr
|
$2.36 | |
| Electricity Fees | $552 | - |
|
- | |
| Natural Gas | $37,534 | 3,930 |
MMBtu
|
$9.55 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,050 | 82 |
Tgal
|
$12.80 | |
| Water Disposal | $2,659 | 55 |
Tgal
|
$48.35 | |
| TOTAL YEARLY COSTS | $113,484 | ||||
| RECOMMENDED SAVINGS* | $22,855 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7224: Reduce space conditioning during non-working hours | $12,399 | $3,735 | - | - |
$12,399
-
MMBtu
|
|
| 02 | 2.7224: Reduce space conditioning during non-working hours | $9,974 | - |
$1,262
13,610
kWh
|
- |
$8,712
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $482 | $828 |
$420
4,526
kWh
|
$62
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $22,855 | $4,563 |
$1,682
18,136
kWh
|
$62
-
kW-mo/yr
|
$21,111
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs