| Assessment Year | 2018 |
|---|---|
| Principal Product | Bentonite clay products |
| NAICS | 327992: Ground or Treated Mineral and Earth Manufacturing |
| SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
| Sales Range | $5 M to 10M |
| # of Employees | 40 |
| Plant Area |
10,000
ft2
|
| Annual Production | 100,000
ton
|
| Production Hrs. Annual | 7,508
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $350,752 | 5,350,170 |
kWh
|
$0.066 |
| Electricity Demand | $31,302 | 14,100 |
kW-mo/yr
|
$2.22 |
| Natural Gas | $297,456 | 65,236 |
MMBtu
|
$4.56 |
| TOTAL YEARLY COSTS | $679,510 | |||
| RECOMMENDED SAVINGS* | $632,295 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,549 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.111: Add equipment/ operators to reduce production bottleneck | $599,971 | $264,049 |
$(-669.4)
(-10,210)
kWh
|
- | - | - | $(-337,860.0) | $(-563,100.0) | $1,501,600 | |
| 02 | 2.1116: Improve combustion control capability | $19,372 | $15,000 |
$15,068
229,843
kWh
|
$816
-
kW-mo/yr
|
- |
$3,488
-
MMBtu
|
- | - | - | |
| 03 | 2.2424: Use heat in flue gases to preheat products or materials | $8,796 | $22,888 | - | - | - |
$8,796
-
MMBtu
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,606 | $2,052 |
$2,450
28,493
kWh
|
$101
-
kW-mo/yr
|
$55 | - | - | - | - | |
| 05 | 2.7442: Keep doors and windows shut when not on use | $1,549 | - |
$1,549
23,328
kWh
|
- | - | - | - | - | - | |
| TOTAL RECOMMENDED | $632,295 | $303,989 |
$18,399
271,454
kWh
|
$917
-
kW-mo/yr
|
$55 |
$12,285
-
MMBtu
|
$(-337,860.0) | $(-563,100.0) | $1,501,600 | ||
| TOTAL IMPLEMENTED | $1,549 | - |
$1,549
23,328
kWh
|
- | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs