ITAC Assessment: UU0128
ITAC logo
ITAC Assessment: UU0128
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Medical supplies, Syringes, Catheters
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $5
M
to 10
M
# of Employees 1,500
Plant Area 650,000
ft2
Annual Production 10,000,000
units
Production Hrs. Annual 3,000
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $744,419 15,500,737
kWh
Electricity Demand $517,925 40,926
kW-mo/yr
Electricity Fees $174,017 -
Natural Gas $30,335 24,860
MMBtu
TOTAL YEARLY COSTS $1,466,696
RECOMMENDED SAVINGS* $193,379 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $192,421

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $109,419 $1,693 $75,064
1,386,842
kWh
$24,031
-
kW-mo/yr
$7,671 $2,653
-
MMBtu
02 2.8121: Apply for tax-free status for energy purchases $80,946 $500 - - $80,946 -
03 2.7131: Add area lighting switches $1,227 $2,200 $1,227
25,565
kWh
- - -
04 2.7122: Disconnect ballasts $958 $800 $646
13,455
kWh
$233
-
kW-mo/yr
$78 -
05 2.1233: Analyze flue gas for proper air/fuel ratio $829 - - - - $829
-
MMBtu
TOTAL RECOMMENDED $193,379 $5,193 $76,937
1,425,862
kWh
$24,264
-
kW-mo/yr
$88,695 $3,482
-
MMBtu
TOTAL IMPLEMENTED $192,421 $4,393 $76,291
1,412,407
kWh
$24,031
-
kW-mo/yr
$88,617 $3,482
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs