Assessment Year | 2005 |
---|---|
Principal Product | Printed Material |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
120,000
ft2
|
Annual Production | 25,000
thousand feet
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $17,073 | 620,240 |
kWh
|
$0.028 |
Electricity Demand | $34,159 | 3,466 |
kW-mo/yr
|
$9.86 |
Natural Gas | $46,598 | 7,867 |
MMBtu
|
$5.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,710 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $2,270 | $7,000 | - |
$2,270
-
kW-mo/yr
|
|
02 | 2.4221: Install compressor air intakes in coolest locations | $1,360 | $420 |
$710
25,210
kWh
|
$650
-
kW-mo/yr
|
|
03 | 2.4221: Install compressor air intakes in coolest locations | $330 | $180 |
$80
2,710
kWh
|
$250
-
kW-mo/yr
|
|
04 | 2.6127: Maintain air filters by cleaning or replacement | $250 | $75 |
$130
4,630
kWh
|
$120
-
kW-mo/yr
|
|
05 | 2.3212: Optimize plant power factor | $12,500 | $15,290 | - |
$12,500
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $16,710 | $22,965 |
$920
32,550
kWh
|
$15,790
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs