Assessment Year | 2005 |
---|---|
Principal Product | whey |
NAICS | 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing |
SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
32,500
ft2
|
Annual Production | 25,000,000
lb
|
Production Hrs. Annual | 3,000
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $183,995 | 8,429,759 |
kWh
|
$0.022 |
Electricity Demand | $38,131 | 13,672 |
kW-mo/yr
|
$2.79 |
LPG | $1,262,013 | 2,036,282 |
MMBtu
|
$0.62 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,505 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,095 | $3,040 |
$7,315
269,458
kWh
|
$3,780
-
kW-mo/yr
|
- | |
02 | 2.4224: Upgrade controls on compressors | $5,900 | - |
$5,900
217,320
kWh
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $681 | $2,276 |
$449
16,577
kWh
|
$232
-
kW-mo/yr
|
- | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $23,294 | $70,000 |
$1,930
71,120
kWh
|
$1,874
-
kW-mo/yr
|
$19,490
-
MMBtu
|
|
05 | 2.1213: Direct warmest air to combustion intake | $6,535 | - | - | - |
$6,535
-
MMBtu
|
|
TOTAL RECOMMENDED | $47,505 | $75,316 |
$15,594
574,475
kWh
|
$5,886
-
kW-mo/yr
|
$26,025
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs