Assessment Year | 2004 |
---|---|
Principal Product | Cell culture media |
NAICS | 325414: Biological Product (except Diagnostic) Manufacturing |
SIC | 2836: Biological Products, Except Diagnostic Substances |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
n/a
|
Annual Production | 278,572
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $225,459 | 5,209,667 |
kWh
|
$0.043 |
Electricity Demand | $90,137 | 10,604 |
kW-mo/yr
|
$8.50 |
Natural Gas | $170,407 | 33,623 |
MMBtu
|
$5.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $62,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,570 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $29,620 | $45,000 | - | - |
$29,620
-
MMBtu
|
|
02 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $6,200 | $17,000 |
$6,200
135,130
kWh
|
- | - | |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $1,750 | $5,000 |
$1,750
38,070
kWh
|
- | - | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,620 | $4 |
$2,800
60,950
kWh
|
$(-180.0)
-
kW-mo/yr
|
- | |
05 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $19,210 | $25 | - | - |
$19,210
-
MMBtu
|
|
06 | 2.3191: Use demand controller or load shedder | $3,570 | $12 | - |
$3,570
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $62,970 | $67,041 |
$10,750
234,150
kWh
|
$3,390
-
kW-mo/yr
|
$48,830
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,570 | $12 | - |
$3,570
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs