ITAC Assessment: UU0074
ITAC logo
ITAC Assessment: UU0074
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Cell culture media
NAICS 325414: Biological Product (except Diagnostic) Manufacturing
SIC 2836: Biological Products, Except Diagnostic Substances
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area
n/a
Annual Production 278,572
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $225,459 5,209,667
kWh
Electricity Demand $90,137 10,604
kW-mo/yr
Natural Gas $170,407 33,623
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $62,970 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,570

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2437: Recover waste heat from equipment $29,620 $45,000 - - $29,620
-
MMBtu
02 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $6,200 $17,000 $6,200
135,130
kWh
- -
03 2.7241: Install outside air damper / economizer on hvac unit $1,750 $5,000 $1,750
38,070
kWh
- -
04 2.7447: Install vinyl strip / high speed / air curtain doors $2,620 $4 $2,800
60,950
kWh
$(-180.0)
-
kW-mo/yr
-
05 2.1243: Use heat from boiler blowdown to preheat boiler feed water $19,210 $25 - - $19,210
-
MMBtu
06 2.3191: Use demand controller or load shedder $3,570 $12 - $3,570
-
kW-mo/yr
-
TOTAL RECOMMENDED $62,970 $67,041 $10,750
234,150
kWh
$3,390
-
kW-mo/yr
$48,830
-
MMBtu
TOTAL IMPLEMENTED $3,570 $12 - $3,570
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs