Assessment Year | 2004 |
---|---|
Principal Product | utility trailers |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $1 M to 5M |
# of Employees | 10 |
Plant Area |
27,000
ft2
|
Annual Production | 220
pieces
|
Production Hrs. Annual | 3,380
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,411 | 122,960 |
kWh
|
$0.028 |
Electricity Demand | $5,411 | 664 |
kW-mo/yr
|
$8.15 |
Electricity Fees | $1,386 | - |
|
- |
Natural Gas | $9,313 | 1,795 |
MMBtu
|
$5.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,049 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $739 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2531: Re-size charging openings or add movable cover or door | $2,690 | $3,000 | - | - | - |
$2,690
-
MMBtu
|
- | |
02 | 2.2136: Install / repair insulation on steam lines | $340 | $200 | - | - | - |
$340
-
MMBtu
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $84 | $310 |
$45
1,508
kWh
|
$39
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $241 | $45 |
$131
4,345
kWh
|
$110
-
kW-mo/yr
|
- | - | - | |
05 | 2.3212: Optimize plant power factor | $81 | $270 | - | - | $81 | - | - | |
06 | 2.7124: Make a practice of turning off lights when not needed | $199 | $80 |
$100
3,344
kWh
|
$99
-
kW-mo/yr
|
- | - | - | |
07 | 4.821: Pay bills on time to avoid late fees | $414 | - | - | - | - | - | $414 | |
TOTAL RECOMMENDED | $4,049 | $3,905 |
$276
9,197
kWh
|
$248
-
kW-mo/yr
|
$81 |
$3,030
-
MMBtu
|
$414 | ||
TOTAL IMPLEMENTED | $739 | $355 |
$176
5,853
kWh
|
$149
-
kW-mo/yr
|
- | - | $414 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs