ITAC Assessment: UU0057
ITAC logo
ITAC Assessment: UU0057
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product ice cream
NAICS 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing
SIC 2024: Ice Cream and Frozen Desserts
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area 48,000
ft2
Annual Production 2,125
Tgal
Production Hrs. Annual 2,080
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,278 3,326,880
kWh
Electricity Demand $83,219 10,274
kW-mo/yr
Electricity Fees $15,852 -
Natural Gas $33,380 7,940
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,561 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,110

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $792 $100 $295
9,780
kWh
$497
-
kW-mo/yr
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $829 $20 $309
10,260
kWh
$520
-
kW-mo/yr
- -
03 2.4221: Install compressor air intakes in coolest locations $279 $129 $104
3,459
kWh
$175
-
kW-mo/yr
- -
04 2.2414: Use waste heat from hot flue gases to preheat $2,240 $6,450 - - $2,240
-
MMBtu
-
05 2.2121: Increase amount of condensate returned $4,493 $25,000 - - $4,181
-
MMBtu
$312
-
Tgal
06 2.1233: Analyze flue gas for proper air/fuel ratio $4,110 $2,000 - - $4,110
-
MMBtu
-
07 2.1222: Install turbulators $1,680 $1,747 - - $1,680
-
MMBtu
-
08 2.2136: Install / repair insulation on steam lines $1,320 $809 - - $1,320
-
MMBtu
-
09 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,920 - - $5,920
-
kW-mo/yr
- -
10 2.7124: Make a practice of turning off lights when not needed $398 $20 $151
4,990
kWh
$247
-
kW-mo/yr
- -
11 3.3132: Use reverse osmosis to concentrate material $25,500 $192,450 - - - $25,500
-
Tgal
TOTAL RECOMMENDED $47,561 $228,725 $859
28,489
kWh
$7,359
-
kW-mo/yr
$13,531
-
MMBtu
$25,812
-
Tgal
TOTAL IMPLEMENTED $7,110 $120 $446
14,770
kWh
$6,664
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs