Assessment Year | 2001 |
---|---|
Principal Product | Irrigation equipment |
NAICS |
n/a
|
SIC | 3432: Plumbing Fixture Fittings and Trim |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
83,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $158,839 | 5,205,750 |
kWh
|
$0.031 |
Electricity Demand | $89,580 | 10,625 |
kW-mo/yr
|
$8.43 |
Electricity Fees | $7,041 | - |
|
- |
Natural Gas | $25,502 | 3,315 |
MMBtu
|
$7.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,254 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,685 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $5,685 | $25 | - | - |
$5,685
-
MMBtu
|
- | - | - | - | |
02 | 2.2612: Use cooling tower water instead of refrigeration | $5,740 | $5,000 |
$4,685
152,607
kWh
|
$2,545
-
kW-mo/yr
|
- |
$(-950.0)
-
Tgal
|
- | - | $(-540.0) | |
03 | 2.2623: Minimize condenser cooling water temperature | $2,554 | $11,000 |
$6,351
206,873
kWh
|
$4,007
-
kW-mo/yr
|
- |
$(-4,976.0)
-
Tgal
|
- | - | $(-2,828.0) | |
04 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $1,456 | $800 |
$129
4,200
kWh
|
$266
-
kW-mo/yr
|
$1,061
-
MMBtu
|
- | - | - | - | |
05 | 2.2515: Use optimum thickness insulation | $3,300 | $5,000 |
$2,138
69,644
kWh
|
$1,162
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $392 | $120 |
$254
8,280
kWh
|
$138
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,001 | $1,589 |
$648
21,112
kWh
|
$353
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.2437: Recover waste heat from equipment | $6,950 | $8,846 | - | - |
$6,950
-
MMBtu
|
- | - | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,215 | $18,300 |
$7,911
257,700
kWh
|
$4,304
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.4133: Use most efficient type of electric motors | $1,136 | $2,093 |
$736
23,959
kWh
|
$400
-
kW-mo/yr
|
- | - | - | - | - | |
11 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $825 | - | - | - | - | - |
$1,650
-
lb
|
$(-825.0) | - | |
TOTAL RECOMMENDED | $41,254 | $52,773 |
$22,852
744,375
kWh
|
$13,175
-
kW-mo/yr
|
$13,696
-
MMBtu
|
$(-5,926.0)
-
Tgal
|
$1,650
-
lb
|
$(-825.0) | $(-3,368.0) | ||
TOTAL IMPLEMENTED | $5,685 | $25 | - | - |
$5,685
-
MMBtu
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs