ITAC Assessment: NC0212
ITAC logo
ITAC Assessment: NC0212
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Irrigation equipment
NAICS
n/a
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 83,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $158,839 5,205,750
kWh
Electricity Demand $89,580 10,625
kW-mo/yr
Electricity Fees $7,041 -
Natural Gas $25,502 3,315
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,254 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,685

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $5,685 $25 - - $5,685
-
MMBtu
- - - -
02 2.2612: Use cooling tower water instead of refrigeration $5,740 $5,000 $4,685
152,607
kWh
$2,545
-
kW-mo/yr
- $(-950.0)
-
Tgal
- - $(-540.0)
03 2.2623: Minimize condenser cooling water temperature $2,554 $11,000 $6,351
206,873
kWh
$4,007
-
kW-mo/yr
- $(-4,976.0)
-
Tgal
- - $(-2,828.0)
04 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $1,456 $800 $129
4,200
kWh
$266
-
kW-mo/yr
$1,061
-
MMBtu
- - - -
05 2.2515: Use optimum thickness insulation $3,300 $5,000 $2,138
69,644
kWh
$1,162
-
kW-mo/yr
- - - - -
06 2.7111: Reduce illumination to minimum necessary levels $392 $120 $254
8,280
kWh
$138
-
kW-mo/yr
- - - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,001 $1,589 $648
21,112
kWh
$353
-
kW-mo/yr
- - - - -
08 2.2437: Recover waste heat from equipment $6,950 $8,846 - - $6,950
-
MMBtu
- - - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $12,215 $18,300 $7,911
257,700
kWh
$4,304
-
kW-mo/yr
- - - - -
10 2.4133: Use most efficient type of electric motors $1,136 $2,093 $736
23,959
kWh
$400
-
kW-mo/yr
- - - - -
11 3.5315: Lease / purchase baler; sell cardboard to recycler $825 - - - - - $1,650
-
lb
$(-825.0) -
TOTAL RECOMMENDED $41,254 $52,773 $22,852
744,375
kWh
$13,175
-
kW-mo/yr
$13,696
-
MMBtu
$(-5,926.0)
-
Tgal
$1,650
-
lb
$(-825.0) $(-3,368.0)
TOTAL IMPLEMENTED $5,685 $25 - - $5,685
-
MMBtu
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs