ITAC Assessment: UU0054
ITAC logo
ITAC Assessment: UU0054
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product mattresses
NAICS 337910: Mattress Manufacturing
SIC 3764: Guided Missile and Space Vehicle Propulsion Units and Propulsion Unit Parts
Sales Range $5
M
to 10
M
# of Employees 47
Plant Area 94,000
ft2
Annual Production 48,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $13,999 498,360
kWh
Electricity Demand $18,845 2,361
kW-mo/yr
Electricity Fees $5,847 -
Natural Gas $13,678 2,376
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,078 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.2437: Recover waste heat from equipment $170 $698 n/a - - - $170
-
MMBtu
02 2.4221: Install compressor air intakes in coolest locations $185 $130 n/a $69
2,300
kWh
$116
-
kW-mo/yr
- -
03 2.7111: Reduce illumination to minimum necessary levels $3,707 - n/a $1,381
42,557
kWh
$2,326
-
kW-mo/yr
- -
04 2.3212: Optimize plant power factor $1,487 $720 n/a - - $1,487 -
05 2.7243: Improve air circulation with destratification fans / other methods $3,909 $3,500 n/a $(-92.0)
(-2,822)
kWh
$(-41.0)
-
kW-mo/yr
- $4,042
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $868 $10,415 n/a $324
9,964
kWh
$544
-
kW-mo/yr
- -
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,752 - n/a - $3,752
-
kW-mo/yr
- -
TOTAL RECOMMENDED $14,078 $15,463 $1,682
51,999
kWh
$6,697
-
kW-mo/yr
$1,487 $4,212
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs