| Assessment Year | 2003 |
|---|---|
| Principal Product | aircraft parts |
| NAICS | 332912: Fluid Power Valve and Hose Fitting Manufacturing |
| SIC | 3720: |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
253,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,919 | 2,016,040 |
kWh
|
$0.028 |
| Electricity Demand | $66,955 | 7,644 |
kW-mo/yr
|
$8.76 |
| Electricity Fees | $12,535 | - |
|
- |
| Natural Gas | $58,727 | 12,996 |
MMBtu
|
$4.52 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,174 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,216 | $5,500 |
$2,834
93,100
kWh
|
$2,382
-
kW-mo/yr
|
- | - | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,838 | $2,000 | - | - | - |
$5,838
-
MMBtu
|
|
| 03 | 2.2437: Recover waste heat from equipment | $1,640 | $4,342 | - | - | - |
$1,640
-
MMBtu
|
|
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,075 | $420 |
$583
19,159
kWh
|
$492
-
kW-mo/yr
|
- | - | |
| 05 | 2.2511: Insulate bare equipment | $177 | $390 | - | - | - |
$177
-
MMBtu
|
|
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,400 | - | - |
$6,400
-
kW-mo/yr
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,684 | $895 |
$914
30,099
kWh
|
$770
-
kW-mo/yr
|
- | - | |
| 08 | 2.3212: Optimize plant power factor | $5,144 | $9,200 | - | - | $5,144 | - | |
| TOTAL RECOMMENDED | $27,174 | $22,747 |
$4,331
142,358
kWh
|
$10,044
-
kW-mo/yr
|
$5,144 |
$7,655
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs