ITAC Assessment: SD0403
ITAC logo
ITAC Assessment: SD0403
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product valves
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 450
Plant Area 246,000
ft2
Annual Production 3
units
Production Hrs. Annual 5,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $800,244 8,693,126
kWh
Electricity Demand $309,773 73,873
kW-mo/yr
Electricity Fees $337,544 -
Natural Gas $42,675 4,496
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $230,506 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $169,607

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $148,069 $13,073 $148,069
1,124,145
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $13,157 $15,033 $11,334
86,122
kWh
$1,823
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,381 $13,275 $8,381
63,686
kWh
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,873 $6,500 $2,873
21,831
kWh
- -
05 2.2414: Use waste heat from hot flue gases to preheat $58,026 $12,356 - - $58,026
-
MMBtu
TOTAL RECOMMENDED $230,506 $60,237 $170,657
1,295,784
kWh
$1,823
-
kW-mo/yr
$58,026
-
MMBtu
TOTAL IMPLEMENTED $169,607 $41,381 $167,784
1,273,953
kWh
$1,823
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs