| Assessment Year | 2008 |
|---|---|
| Principal Product | valves |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 450 |
| Plant Area |
246,000
ft2
|
| Annual Production | 3
units
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $800,244 | 8,693,126 |
kWh
|
$0.092 |
| Electricity Demand | $309,773 | 73,873 |
kW-mo/yr
|
$4.19 |
| Electricity Fees | $337,544 | - |
|
- |
| Natural Gas | $42,675 | 4,496 |
MMBtu
|
$9.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $230,506 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $169,607 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $148,069 | $13,073 |
$148,069
1,124,145
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,157 | $15,033 |
$11,334
86,122
kWh
|
$1,823
-
kW-mo/yr
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,381 | $13,275 |
$8,381
63,686
kWh
|
- | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,873 | $6,500 |
$2,873
21,831
kWh
|
- | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $58,026 | $12,356 | - | - |
$58,026
-
MMBtu
|
|
| TOTAL RECOMMENDED | $230,506 | $60,237 |
$170,657
1,295,784
kWh
|
$1,823
-
kW-mo/yr
|
$58,026
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $169,607 | $41,381 |
$167,784
1,273,953
kWh
|
$1,823
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs