Assessment Year | 2003 |
---|---|
Principal Product | vinyl windows and fencing |
NAICS | 331318: Other Aluminum Rolling, Drawing, and Extruding |
SIC | 3354: Aluminum Extruded Products |
Sales Range | $10 M to 50M |
# of Employees | 30 |
Plant Area |
160,000
ft2
|
Annual Production | 8,500,000
lb
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $51,562 | 1,858,960 |
kWh
|
$0.028 |
Electricity Demand | $45,684 | 4,856 |
kW-mo/yr
|
$9.41 |
Natural Gas | $11,126 | 2,383 |
MMBtu
|
$4.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,894 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $15,620 | $8,000 | - | - | $15,620 | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,027 | $1,500 |
$680
24,000
kWh
|
$347
-
kW-mo/yr
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $632 | $550 |
$124
4,400
kWh
|
$508
-
kW-mo/yr
|
- | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $9,960 | - | - |
$9,960
-
kW-mo/yr
|
- | - | |
05 | 2.4133: Use most efficient type of electric motors | $2,836 | $20,051 |
$1,878
66,065
kWh
|
$958
-
kW-mo/yr
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $420 | $406 |
$278
9,781
kWh
|
$142
-
kW-mo/yr
|
- | - | |
07 | 2.2437: Recover waste heat from equipment | $792 | $2,296 | - | - | - |
$792
-
MMBtu
|
|
08 | 2.2628: Utilize a less expensive cooling method | $14,607 | $100,240 |
$9,670
342,188
kWh
|
$4,937
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $45,894 | $133,043 |
$12,630
446,434
kWh
|
$16,852
-
kW-mo/yr
|
$15,620 |
$792
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs