Assessment Year | 2002 |
---|---|
Principal Product | candy |
NAICS |
n/a
|
SIC | 2064: Candy and Other Confectionery Products |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
n/a
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $159,847 | 5,847,900 |
kWh
|
$0.027 |
Electricity Demand | $111,612 | 13,980 |
kW-mo/yr
|
$7.98 |
Electricity Fees | $30,160 | - |
|
- |
Natural Gas | $151,487 | 31,656 |
MMBtu
|
$4.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,759 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1211: Move boiler to more efficient location | $83 | $86 | - | - |
$83
-
MMBtu
|
|
02 | 2.7243: Improve air circulation with destratification fans / other methods | $4,155 | $12,000 |
$(-239.0)
(-9,585)
kWh
|
$238
-
kW-mo/yr
|
$4,156
-
MMBtu
|
|
03 | 2.3212: Optimize plant power factor | $988 | $2,604 | - |
$988
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $4,743 | $600 |
$2,712
89,987
kWh
|
$2,031
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,517 | $17,563 |
$2,582
85,715
kWh
|
$1,935
-
kW-mo/yr
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,273 | $343 |
$810
26,620
kWh
|
$463
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $15,759 | $33,196 |
$5,865
192,737
kWh
|
$5,655
-
kW-mo/yr
|
$4,239
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs