ITAC Assessment: UU0032
ITAC logo
ITAC Assessment: UU0032
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product candy
NAICS
n/a
SIC 2064: Candy and Other Confectionery Products
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area
n/a
Annual Production 0
pieces
Production Hrs. Annual 4,080
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $159,847 5,847,900
kWh
Electricity Demand $111,612 13,980
kW-mo/yr
Electricity Fees $30,160 -
Natural Gas $151,487 31,656
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,759 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1211: Move boiler to more efficient location $83 $86 - - $83
-
MMBtu
02 2.7243: Improve air circulation with destratification fans / other methods $4,155 $12,000 $(-239.0)
(-9,585)
kWh
$238
-
kW-mo/yr
$4,156
-
MMBtu
03 2.3212: Optimize plant power factor $988 $2,604 - $988
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $4,743 $600 $2,712
89,987
kWh
$2,031
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,517 $17,563 $2,582
85,715
kWh
$1,935
-
kW-mo/yr
-
06 2.4221: Install compressor air intakes in coolest locations $1,273 $343 $810
26,620
kWh
$463
-
kW-mo/yr
-
TOTAL RECOMMENDED $15,759 $33,196 $5,865
192,737
kWh
$5,655
-
kW-mo/yr
$4,239
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs