ITAC Assessment: UU0030
ITAC logo
ITAC Assessment: UU0030
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product boxes
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $1
M
to 5
M
# of Employees 38
Plant Area 35,000
ft2
Annual Production 29,000
thousand feet
Production Hrs. Annual 2,625
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $5,861 215,520
kWh
Electricity Demand $9,653 1,032
kW-mo/yr
Electricity Fees $3,264 -
Natural Gas $8,004 1,326
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,281 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,085

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $1,624 $1,800 - $1,624
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,250 $390 $460
14,300
kWh
$790
-
kW-mo/yr
-
03 2.4221: Install compressor air intakes in coolest locations $379 $240 $162
5,027
kWh
$217
-
kW-mo/yr
-
04 2.7243: Improve air circulation with destratification fans / other methods $929 $200 $(-106.0)
(-3,288)
kWh
$(-149.0)
-
kW-mo/yr
$1,184
-
MMBtu
05 2.4133: Use most efficient type of electric motors $1,080 $1,843 $454
14,083
kWh
$626
-
kW-mo/yr
-
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $808 - $339
10,490
kWh
$469
-
kW-mo/yr
-
07 2.4314: Use synthetic lubricant $1,211 $600 $508
15,735
kWh
$703
-
kW-mo/yr
-
TOTAL RECOMMENDED $7,281 $5,073 $1,817
56,347
kWh
$4,280
-
kW-mo/yr
$1,184
-
MMBtu
TOTAL IMPLEMENTED $4,085 $2,790 $968
30,035
kWh
$3,117
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs