| Assessment Year | 2002 |
|---|---|
| Principal Product | Irrgation Products |
| NAICS |
n/a
|
| SIC | 3342: |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
340,800
ft2
|
| Annual Production | 8,000,000
pieces
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $88,443 | 3,288,240 |
kWh
|
$0.027 |
| Electricity Demand | $76,020 | 747 |
kW-mo/yr
|
$101.77 |
| Electricity Fees | $28,577 | - |
|
- |
| Natural Gas | $66,005 | 11,655 |
MMBtu
|
$5.66 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,101 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,374 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,326 | $9,484 |
$4,309
134,709
kWh
|
$2,017
-
kW-mo/yr
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,774 | $180 |
$1,002
33,262
kWh
|
$772
-
kW-mo/yr
|
|
| 03 | 2.4221: Install compressor air intakes in coolest locations | $631 | $442 |
$364
11,644
kWh
|
$267
-
kW-mo/yr
|
|
| 04 | 2.3212: Optimize plant power factor | $6,600 | $4,500 | - |
$6,600
-
kW-mo/yr
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,770 | $12,000 |
$9,380
293,268
kWh
|
$4,390
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $29,101 | $26,606 |
$15,055
472,883
kWh
|
$14,046
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $8,374 | $4,680 |
$1,002
33,262
kWh
|
$7,372
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs