ITAC Assessment: UU0015
ITAC logo
ITAC Assessment: UU0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Linen suppliers
NAICS
n/a
SIC 2389: Apparel and Accessories, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area 15,000
ft2
Annual Production 5,200,000
lb
Production Hrs. Annual 4,590
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $11,449 277,040
kWh
Electricity Demand $5,719 1,236
kW-mo/yr
Electricity Fees $2,176 -
Natural Gas $92,644 14,641
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,864 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $173 $141 $100
3,602
kWh
$73
-
kW-mo/yr
-
02 2.2511: Insulate bare equipment $422 $625 - - $422
-
MMBtu
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,040 - $673
24,389
kWh
$367
-
kW-mo/yr
-
04 2.4314: Use synthetic lubricant $1,715 $800 $1,110
40,199
kWh
$605
-
kW-mo/yr
-
05 2.4133: Use most efficient type of electric motors $1,486 $5,165 $843
30,933
kWh
$643
-
kW-mo/yr
-
06 2.7124: Make a practice of turning off lights when not needed $839 - $486
17,604
kWh
$353
-
kW-mo/yr
-
07 2.1116: Improve combustion control capability $12,189 $21,500 - - $12,189
-
MMBtu
TOTAL RECOMMENDED $17,864 $28,231 $3,212
116,727
kWh
$2,041
-
kW-mo/yr
$12,611
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs