Assessment Year | 2001 |
---|---|
Principal Product | Hydraulic flight control systems |
NAICS |
n/a
|
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 1,000 |
Plant Area |
270,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 4,590
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $352,223 | 14,215,400 |
kWh
|
$0.025 |
Electricity Demand | $205,572 | 29,412 |
kW-mo/yr
|
$6.99 |
Electricity Fees | $(-9,637.0) | - |
|
- |
Natural Gas | $35,553 | 17,369 |
MMBtu
|
$2.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,365 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,365 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $12,515 | $19,380 | - |
$12,515
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,476 | $18,287 |
$6,449
226,220
kWh
|
$3,027
-
kW-mo/yr
|
- | |
03 | 2.2437: Recover waste heat from equipment | $3,538 | $1,000 |
$2,580
90,488
kWh
|
$958
-
kW-mo/yr
|
- | |
04 | 2.2437: Recover waste heat from equipment | $560 | $650 | - | - |
$560
-
MMBtu
|
|
05 | 2.4314: Use synthetic lubricant | $1,276 | $600 |
$930
32,631
kWh
|
$346
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $27,365 | $39,917 |
$9,959
349,339
kWh
|
$16,846
-
kW-mo/yr
|
$560
-
MMBtu
|
||
TOTAL IMPLEMENTED | $27,365 | $39,917 |
$9,959
349,339
kWh
|
$16,846
-
kW-mo/yr
|
$560
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs