Assessment Year | 2014 |
---|---|
Principal Product | Hydraulic fittings |
NAICS | 332912: Fluid Power Valve and Hose Fitting Manufacturing |
SIC | 3492: Fluid Power Valves and Hose Fittings |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
46,000
ft2
|
Annual Production | 7,147,705
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $221,099 | 1,860,706 |
kWh
|
$0.12 |
Natural Gas | $17,808 | 2,259 |
MMBtu
|
$7.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,992 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,992 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,365 | $500 |
$3,365
24,350
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,543 | $6,000 |
$1,543
11,162
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $2,152 | $2,500 |
$2,152
16,881
kWh
|
- | |
04 | 2.2437: Recover waste heat from equipment | $2,534 | $1,500 | - |
$2,534
-
MMBtu
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,089 | $500 |
$1,089
10,804
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $865 | $3,750 |
$865
8,580
kWh
|
- | |
07 | 2.4221: Install compressor air intakes in coolest locations | $486 | $1,250 |
$486
4,817
kWh
|
- | |
08 | 2.2437: Recover waste heat from equipment | $958 | $750 | - |
$958
-
MMBtu
|
|
TOTAL RECOMMENDED | $12,992 | $16,750 |
$9,500
76,594
kWh
|
$3,492
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,992 | $16,750 |
$9,500
76,594
kWh
|
$3,492
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs