Assessment Year | 2013 |
---|---|
Principal Product | tools, forms for plastic molding |
NAICS | 331410: Nonferrous Metal (except Aluminum) Smelting and Refining |
SIC | 3339: Primary Smelting and Refining of Nonferrous Metals, Except Copper and Aluminum |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
120,000
ft2
|
Annual Production | 20,000
units
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $203,812 | 3,396,089 |
kWh
|
$0.060 |
Electricity Demand | $119,451 | 9,105 |
kW-mo/yr
|
$13.12 |
Electricity Fees | $60,627 | - |
|
- |
Natural Gas | $35,296 | 5,496 |
MMBtu
|
$6.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,916 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,416 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2622: Replace existing chiller with high efficiency model | $4,450 | $4,500 |
$3,500
57,000
kWh
|
$950
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,500 | $200 |
$3,500
55,426
kWh
|
$1,000
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $966 | $2,500 |
$843
13,800
kWh
|
$124
-
kW-mo/yr
|
- | |
04 | 2.2437: Recover waste heat from equipment | $2,000 | $3,000 | - | - |
$2,000
-
MMBtu
|
|
TOTAL RECOMMENDED | $11,916 | $10,200 |
$7,843
126,226
kWh
|
$2,074
-
kW-mo/yr
|
$2,000
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,416 | $10,000 |
$4,343
70,800
kWh
|
$1,074
-
kW-mo/yr
|
$2,000
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs