| Assessment Year | 2012 |
|---|---|
| Principal Product | heavy plate weldments and steel& aluminum plate burning |
| NAICS | 332313: Plate Work Manufacturing |
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $10 M to 50M |
| # of Employees | 145 |
| Plant Area |
100,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,500
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $115,000 | 2,110,000 |
kWh
|
$0.055 |
| Electricity Demand | $69,000 | 6,936 |
kW-mo/yr
|
$9.95 |
| Natural Gas | $58,700 | 8,140 |
MMBtu
|
$7.21 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,025 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,025 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4224: Upgrade controls on compressors | $5,760 | $200 |
$5,760
104,000
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,275 | $1,300 |
$4,000
72,800
kWh
|
$1,275
-
kW-mo/yr
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $500 | $1,000 |
$260
4,750
kWh
|
$240
-
kW-mo/yr
|
- | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $3,480 | $3,200 |
$480
8,700
kWh
|
$3,000
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,010 | $15,800 |
$2,594
47,159
kWh
|
$1,416
-
kW-mo/yr
|
- | |
| 06 | 2.7314: Reduce ventilation air | $11,000 | $10,000 | - | - |
$11,000
-
MMBtu
|
|
| TOTAL RECOMMENDED | $30,025 | $31,500 |
$13,094
237,409
kWh
|
$5,931
-
kW-mo/yr
|
$11,000
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $30,025 | $31,500 |
$13,094
237,409
kWh
|
$5,931
-
kW-mo/yr
|
$11,000
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs