| Assessment Year | 2011 |
|---|---|
| Principal Product | Flexible plastic packaging |
| NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
| SIC | 2673: Plastics, Foil, and Coated Paper Bags |
| Sales Range | $50 M to 100M |
| # of Employees | 158 |
| Plant Area |
140,000
ft2
|
| Annual Production | 12,094
ton
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $474,967 | 8,488,094 |
kWh
|
$0.056 |
| Electricity Demand | $255,564 | 17,159 |
kW-mo/yr
|
$14.89 |
| Natural Gas | $177,405 | 37,574 |
MMBtu
|
$4.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $70,662 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $6,323 | $5,000 |
$4,179
74,675
kWh
|
$2,144
-
kW-mo/yr
|
- | |
| 02 | 2.4224: Upgrade controls on compressors | $8,974 | $8,890 |
$5,936
106,080
kWh
|
$3,038
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,425 | $15,571 |
$1,606
28,691
kWh
|
$819
-
kW-mo/yr
|
- | |
| 04 | 2.2437: Recover waste heat from equipment | $51,920 | $110,521 | - | - |
$51,920
-
MMBtu
|
|
| 05 | 2.2447: Heat water with exhaust heat | $798 | $2,261 | - | - |
$798
-
MMBtu
|
|
| 06 | 2.2136: Install / repair insulation on steam lines | $222 | $161 | - | - |
$222
-
MMBtu
|
|
| TOTAL RECOMMENDED | $70,662 | $142,404 |
$11,721
209,446
kWh
|
$6,001
-
kW-mo/yr
|
$52,940
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs