Assessment Year | 2011 |
---|---|
Principal Product | Engine Testing |
NAICS | 541380: Testing Laboratories |
SIC | 8734: Testing Laboratories |
Sales Range | $10 M to 50M |
# of Employees | 61 |
Plant Area |
24,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $190,410 | 4,010,190 |
kWh
|
$0.047 |
Electricity Demand | $135,138 | 6,689 |
kW-mo/yr
|
$20.20 |
Natural Gas | $27,831 | 3,054 |
MMBtu
|
$9.11 |
Other Energy | $1,203,200 | 45,669 |
MMBtu
|
$26.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $107,176 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $68,681 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $25,825 | $18,696 |
$17,369
365,811
kWh
|
$8,456
-
kW-mo/yr
|
- | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $14,190 | $18,432 |
$8,960
188,718
kWh
|
$5,230
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,125 | $29,225 |
$7,654
161,201
kWh
|
$4,471
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $7,581 | $2,500 |
$4,789
100,868
kWh
|
$2,792
-
kW-mo/yr
|
- | - | |
05 | 2.4224: Upgrade controls on compressors | $7,039 | $6,006 |
$4,450
93,732
kWh
|
$2,589
-
kW-mo/yr
|
- | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,888 | $5,440 |
$2,481
52,259
kWh
|
$2,407
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,578 | $200 |
$2,263
47,669
kWh
|
$1,315
-
kW-mo/yr
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,408 | $1,533 |
$2,154
45,363
kWh
|
$1,254
-
kW-mo/yr
|
- | - | |
09 | 2.7135: Install occupancy sensors | $1,916 | $1,200 |
$1,916
40,357
kWh
|
- | - | - | |
10 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $10,545 | $23,900 | - | - |
$10,545
-
MMBtu
|
- | |
11 | 2.2437: Recover waste heat from equipment | $3,143 | $2,500 | - | - |
$3,143
-
MMBtu
|
- | |
12 | 2.2511: Insulate bare equipment | $12,938 | $600 | - | - | - |
$12,938
-
MMBtu
|
|
TOTAL RECOMMENDED | $107,176 | $110,232 |
$52,036
1,095,978
kWh
|
$28,514
-
kW-mo/yr
|
$13,688
-
MMBtu
|
$12,938
-
MMBtu
|
||
TOTAL IMPLEMENTED | $68,681 | $59,194 |
$36,363
765,859
kWh
|
$19,380
-
kW-mo/yr
|
- |
$12,938
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs