ITAC Assessment: SF0564
ITAC logo
ITAC Assessment: SF0564
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Treated Water
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $50
M
to 100
M
# of Employees 46
Plant Area 290,000
ft2
Annual Production 4,929,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $111,334 959,776
kWh
Electricity Demand $336,402 10,512
kW-mo/yr
Natural Gas $262,424 44,087
MMBtu
Fuel Oil #1 $128 5
MMBtu
TOTAL YEARLY COSTS $710,288
RECOMMENDED SAVINGS* $1,079,155 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $74,027

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #1 Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,530 - $12
3,564
kWh
$2,518
-
kW-mo/yr
- - - -
02 2.7224: Reduce space conditioning during non-working hours $8,683 $748 $8,683
74,854
kWh
- - - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,060 $149 $1,060
9,139
kWh
- - - - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $192,090 $88,600 $131,859
1,136,717
kWh
$60,231
-
kW-mo/yr
- - - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $33,128 $15,421 $33,128
285,589
kWh
- - - - -
06 2.3323: Install emissions controls to increase capacity $352,407 $278,000 $280,667
2,419,545
kWh
$71,740
-
kW-mo/yr
- - - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $24,296 $18,341 $24,296
209,454
kWh
- - - - -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $77,855 $69,051 $77,855
671,169
kWh
- - - - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $78,185 $114,380 $55,615
479,442
kWh
$22,570
-
kW-mo/yr
- - - -
10 2.3142: User battery storage for power quality issues $262,606 $452,925 - $291,950
-
kW-mo/yr
$(-22,344.0)
-
MMBtu
$(-7,000.0)
-
MMBtu
- -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $26,256 $50,039 $19,042
163,089
kWh
$5,393
-
kW-mo/yr
- - $1,279 $542
12 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,006 $31,025 $9,006
77,635
kWh
- - - - -
13 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,053 $65,832 $11,053
95,287
kWh
- - - - -
TOTAL RECOMMENDED $1,079,155 $1,184,511 $652,276
5,625,484
kWh
$454,402
-
kW-mo/yr
$(-22,344.0)
-
MMBtu
$(-7,000.0)
-
MMBtu
$1,279 $542
TOTAL IMPLEMENTED $74,027 $131,441 $64,295
556,668
kWh
$7,911
-
kW-mo/yr
- - $1,279 $542
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #1 Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs