| Assessment Year | 1996 |
|---|---|
| Principal Product | Finished Leather |
| NAICS |
n/a
|
| SIC | 3111: Leather Tanning and Finishing |
| Sales Range | $10 M to 50M |
| # of Employees | 550 |
| Plant Area |
240,000
ft2
|
| Annual Production | 2,925,000
pieces
|
| Production Hrs. Annual | 5,800
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $887,619 | 13,377,784 |
kWh
|
$0.066 |
| Electricity Demand | $292,939 | 28,185 |
kW-mo/yr
|
$10.39 |
| Electricity Fees | $48,506 | - |
|
- |
| LPG | $61,471 | 12,689 |
MMBtu
|
$4.84 |
| Fuel Oil #6 | $679,867 | 203,948 |
MMBtu
|
$3.33 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $159,255 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $120,715 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #6 Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $29,559 | $75,922 |
$23,834
340,563
kWh
|
$5,725
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.3511: Use plant owned transformers or lease transformers | $18,340 | $106,350 | - | - | - | - | - | $18,340 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,372 | $350 |
$14,372
205,451
kWh
|
- | - | - | - | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,115 | $8,175 |
$12,115
172,919
kWh
|
- | - | - | - | - | |
| 05 | 2.1331: Burn a less expensive grade of fuel | $9,328 | $4,581 | - | - |
$49,133
-
MMBtu
|
$(-39,805.0)
-
MMBtu
|
- | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $10,872 | $4,125 |
$11,225
165,592
kWh
|
$(-353.0)
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.2136: Install / repair insulation on steam lines | $1,368 | $640 | - | - | - |
$1,368
-
MMBtu
|
- | - | |
| 08 | 2.2511: Insulate bare equipment | $1,143 | $570 | - | - | - |
$1,143
-
MMBtu
|
- | - | |
| 09 | 2.2511: Insulate bare equipment | $123 | $150 |
$123
1,758
kWh
|
- | - | - | - | - | |
| 10 | 3.4151: Minimize water usage | $59,250 | $15,500 | - | - | - | - |
$59,250
-
Tgal
|
- | |
| 11 | 3.4151: Minimize water usage | $2,785 | $30 | - | - | - | - |
$2,785
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $159,255 | $216,393 |
$61,669
886,283
kWh
|
$5,372
-
kW-mo/yr
|
$49,133
-
MMBtu
|
$(-37,294.0)
-
MMBtu
|
$62,035
-
Tgal
|
$18,340 | ||
| TOTAL IMPLEMENTED | $120,715 | $101,337 |
$50,444
720,691
kWh
|
$5,725
-
kW-mo/yr
|
- |
$2,511
-
MMBtu
|
$62,035
-
Tgal
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #6 Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs