ITAC Assessment: ME0194
ITAC logo
ITAC Assessment: ME0194
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Finished Leather
NAICS
n/a
SIC 3111: Leather Tanning and Finishing
Sales Range $10
M
to 50
M
# of Employees 550
Plant Area 240,000
ft2
Annual Production 2,925,000
pieces
Production Hrs. Annual 5,800
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $887,619 13,377,784
kWh
Electricity Demand $292,939 28,185
kW-mo/yr
Electricity Fees $48,506 -
LPG $61,471 12,689
MMBtu
Fuel Oil #6 $679,867 203,948
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $159,255 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $120,715

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Fuel Oil #6 Savings Water Disposal Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $29,559 $75,922 $23,834
340,563
kWh
$5,725
-
kW-mo/yr
- - - -
02 2.3511: Use plant owned transformers or lease transformers $18,340 $106,350 - - - - - $18,340
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $14,372 $350 $14,372
205,451
kWh
- - - - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $12,115 $8,175 $12,115
172,919
kWh
- - - - -
05 2.1331: Burn a less expensive grade of fuel $9,328 $4,581 - - $49,133
-
MMBtu
$(-39,805.0)
-
MMBtu
- -
06 2.4239: Eliminate or reduce compressed air usage $10,872 $4,125 $11,225
165,592
kWh
$(-353.0)
-
kW-mo/yr
- - - -
07 2.2136: Install / repair insulation on steam lines $1,368 $640 - - - $1,368
-
MMBtu
- -
08 2.2511: Insulate bare equipment $1,143 $570 - - - $1,143
-
MMBtu
- -
09 2.2511: Insulate bare equipment $123 $150 $123
1,758
kWh
- - - - -
10 3.4151: Minimize water usage $59,250 $15,500 - - - - $59,250
-
Tgal
-
11 3.4151: Minimize water usage $2,785 $30 - - - - $2,785
-
Tgal
-
TOTAL RECOMMENDED $159,255 $216,393 $61,669
886,283
kWh
$5,372
-
kW-mo/yr
$49,133
-
MMBtu
$(-37,294.0)
-
MMBtu
$62,035
-
Tgal
$18,340
TOTAL IMPLEMENTED $120,715 $101,337 $50,444
720,691
kWh
$5,725
-
kW-mo/yr
- $2,511
-
MMBtu
$62,035
-
Tgal
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Fuel Oil #6 Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs